3D Modelling Tank Upgrade

Year: 2018
Duration: 4 Weeks
Value: £10k
Industry: Chemial

We completed the 3D Modelling and Visualisation for a chemical plant in Manchester. The design was to provide a new Chemical Storage Tank with IBC filling station.

Water Treatment Plant Upgrade

Year: 2018
Duration: 8 Weeks
Value: £25k
Industry: Water

As part of an existing plant process improvement, Deans Design Services Limited were approached to design and build a new dosing control panel for a Water treatment site in Cheshire.

We had to provide a fast turnaound to install a new PLC control system to control a plant that was using a legacy PLC system that was no longer being supported, we were asked to completed the design of the Control Panel Design along with new plant control software, Installation and Commissioning.